Create a rebuilding budget before committing to a new home design
The short answer: Before committing to a design, homeowners should prepare a rebuilding budget showing the funds likely to be available, by insurance category, and every cost those funds must cover, including professional fees, permits, site work, a contingency and a reserve for temporary housing. An architect cannot reliably design to a budget without a clear financial target, and discovering a project is over budget after construction drawings are finished can force an expensive redesign.
Key takeaways
- Insurance proceeds come in categories with different limits and conditions.
- Construction cost is only part of the project cost.
- Protect a housing reserve in case living expense coverage ends before completion.
Many fire survivors begin the rebuilding process by meeting with an architect and discussing what they want their new home to look like. That is understandable, but it may put design decisions ahead of financial reality.
Before committing to a design, homeowners should prepare a comprehensive rebuilding budget showing the funds likely to be available and the expenses those funds must cover.
Start with the insurance policy
Insurance proceeds are frequently divided among several categories, including the dwelling, other structures, personal property and additional living expenses. These categories may have different limits and payment requirements.
Homeowners should determine:
- The dwelling policy limit and any extended replacement coverage
- Whether building code or ordinance coverage is available
- What documentation the insurer requires
- Whether depreciation can be recovered after replacement
- Whether a mortgage lender must approve or release payments
- How long additional living expense benefits may continue
An insurer’s estimate is not necessarily the same as the actual cost of rebuilding. Homeowners should compare the insurer’s estimate with proposals from experienced architects and contractors.
Include the entire project cost
Construction costs are only one part of the budget. A realistic plan may also need to account for architectural and engineering fees, surveys, soil testing, permits, utility work, temporary fencing, landscaping, insurance, financing costs and professional consulting fees.
The budget should also contain a contingency reserve. Existing site conditions, material prices and design changes can increase costs even when the project has been carefully planned.
Coordinate the design with the budget
An architect cannot reliably design to a budget unless the homeowner provides a clear financial target. The architect and contractor should understand whether that target includes professional fees and other “soft costs” or applies only to construction.
It can be helpful to obtain preliminary pricing at several points during design. Discovering that a project is substantially over budget after the construction drawings have been completed may force the homeowner to pay for an expensive redesign.
Protect funds needed for temporary housing
A homeowner should also consider how long the rebuilding process may take. Permitting and construction can extend well beyond initial expectations.
If additional living expense coverage ends before the home is completed, rent and other temporary expenses may have to be paid from personal funds. Using all available cash for construction without maintaining a housing reserve can therefore create additional pressure.
A plan that carries the family through completion
A rebuilding budget will change as information develops. Nevertheless, preparing one early allows the homeowner to make informed decisions about the size, design and specifications of the replacement home.
The objective is not simply to begin construction. It is to develop a financially workable plan that can carry the family through completion.
Frequently asked questions
What should a fire rebuild budget include besides construction?
Architecture and engineering, surveys, soils reports, permits, utility work, temporary fencing, landscaping, builder’s risk insurance, financing costs, consultants, a contingency, and a reserve for temporary housing.
How much contingency should I include?
It depends on the site, design and market. Discuss a figure with your architect and contractor and revisit it as pricing comes in.
When should I get pricing during design?
Several times: at concept, at schematic design and before construction documents. Early pricing helps avoid an expensive redesign.
Questions about your own claim? Jonathan reviews every request personally. Request a review or get new articles by email.
Related reading
Sources
- California Insurance Code § 2051.5
- California Insurance Code § 2060
- CDI Bulletin 2025-2: wildfire consumer protections
This article provides general information and is not legal, insurance or financial advice. Laws and deadlines change, and how they apply depends on your policy and facts. Reading this article or contacting Bloch Advisory Services does not create an attorney-client relationship. Attorney advertising. Jonathan R. Bloch, Bloch Advisory Services, 9701 Wilshire Blvd., Suite 1000, Beverly Hills, CA 90212.